Guest Editor: 12/15/2018

OVA struggles to control escalating East Rec Center costs



By Michael Connolly, Oakmont resident, co-founder of oakmontobserver.com

At the Nov. 13 Oakmont Village Association (OVA) board meeting, the membership was given an update on the East Recreation Center (ERC) construction project. Two weeks prior to the meeting it had been announced that additional costs of $413,975 via a change order were being added to the budget. Then at the board meeting this amount was supplemented by an additional $102,000 in contingency funds, bringing the latest cost overrun potentially to $515,975 and the total construction costs to $2,778,000.

Add to this the interest and fees on the $1.6 million loan that OVA is using to finance the project and the total cost is over $3 million.

A little over a year ago, in October 2017, Building Construction Committee Chair Iris Harrell gave a cost estimate for the project of $1.5 million. In April of this year a contract was signed with Nordby Construction for $1.734 million. Approved expenditures increased in June to just under $2.3 million, which included four change orders before a shovel even hit the dirt. With the latest change order number six approved last month the project cost has risen more than a million dollars above the original contract price and double the estimate from a year ago.

Four years ago when plans for a West Rec Center remodel were being discussed one OVA board member noted that “every one of the last six or seven major projects came in over estimates.” With the news of yet another OVA construction project being over budget, it raises the question as to whether those entrusted with managing these projects have learned from past experiences and errors in budgeting.

Plans to remodel the West Rec Center (WRC) building and pool area were estimated at $885,000 in 2014 and early 2015. The final cost was $1.365 million, an overrun of 54 percent.

Expensive and unplanned ADA requirements, problems with underground water, electrical and gas lines, as well as unforeseen problems inside the building led to the WRC cost overruns. These are the same issues that are again being claimed as justification for cost overruns on the ERC project, as if they were unexpected or unforeseen.

An OVA member, who did not wish to be named, with many years of experience in construction project management was interviewed for this article and made the following points:

“Any contractor or engineer knows that if you remove a depth of two feet of soil, compaction work will be required when you reinstall new soil. This should have been estimated in the original scope of work and budget.”

In addition, “The huge costs for replacing all the underground utilities should have been in the initial budget. The contractor saved significant excavation costs by being able to excavate without protecting the underground utilities.” New additional costs of $142,506 for further demolition, paving, grading and excavation are included in the current change order. The original contract in April had already included more than $660,000 for these and other site work costs.

“A good project manager tries to avoid change orders as the contractor can basically ‘name their price.’ This project is on change order number six. Looking over the items, they all should have been included in the initial scope.” The fact that Nordby Construction is acting as its own project manager further clouds the issues involving the initial scope of work and the use of numerous change orders.

What can OVA do to guard against these serious cost overruns in the future? The following suggestions were made by two construction project management specialists who were interviewed for this article:

• It appears that the process used to define the scope of work and to budget for construction projects is flawed. The Board should not approve projects that are not clearly defined. Prior to approval by the Board, the project should be 90 percent defined in design and scope before taking bids and submitting plans to the city for permits. This will limit the number and size of change orders, which are expensive and add significantly to costs of the project.

• Contingency funds should be used strictly for unknowns, such as weather delays and unforeseen circumstances, not for changes in scope. In the ERC project, the underground work in the pool area should have been in the original scope and budget, especially since OVA and Nordby Construction encountered similar issues during the WRC pool project.

• Soliciting at least three competitive bids should also be the defined practice for expensive construction projects. In this circumstance, a decision was made over a year ago to solicit a single preconstruction services contract to get the ERC project started as soon as possible in light of the perceived demands for construction services after the fires in Sonoma County. Soliciting single bids for large constructions projects should not become a regular practice.

• For future projects over $1 million, OVA should contract with an independent construction manager to oversee the project. Earlier this year OVA signed a contract with Nordby Construction, the building contractor, in the amount of $146,000 to provide its own “job site management” on the current ERC project. To avoid possible conflicts of interest and to control costs, a certified Project Management Professional project manager should be brought on board prior to signing a design contract. They could assist the board in the project scope definition, contract bidding and the awarding of both design and construction contracts.



Recently Published:

05/15/2019 - Oakmont Golf cents and sensibility
04/01/2019 - The wrong way to plan for cannabis cultivation
03/15/2019 - Referendum needed on any proposed purchase of Oakmont Golf Club
03/01/2019 - Looking back and moving forward with SDC
02/01/2019 - Sonoma County should protect its residents by abiding by the State SRA Fire Safe Regulations
01/15/2019 - Oakmont East Recreation Center is a sound investment
12/15/2018 - OVA struggles to control escalating East Rec Center costs
12/01/2018 - GEFD – Setting the record straight
11/01/2018 - No on Measure T – No blank check
11/01/2018 - Where is Oakmont headed?
11/01/2018 - Yes on Measure T
10/15/2018 - For SDC, let’s try something different
10/15/2018 - Remembering Guardians in the Land of Fire
09/01/2018 - Yellowstone wolves: What happened when they came back, and what could happen here
09/01/2018 - Sonoma Development Center update
09/01/2018 - The promise of SDC: A community call to action
08/15/2018 - Don’t gamble with Oakmont’s future
08/15/2018 - Apothevert should be granted a use permit
08/01/2018 - Keep commercial marijuana away from our parks
08/01/2018 - Oakmont residents should not pay to save Oakmont Golf Club
07/01/2018 - Strangers in paradise
07/01/2018 - What does homelessness feel like?
06/01/2018 - Transforming SDC: Don't tread on us
05/15/2018 - Moving past outrage in Oakmont
04/01/2018 - It’s time to talk redevelopment of the SDC

Community Calendar

Trail work
05/23/2019
more...
Emergency response, CPR training in Glen Ellen
05/25/2019
more...
Sierra Garden now open near Oakmont
05/25/2019
more...
Kenwood Community Church service
05/26/2019
more...
Sugarloaf Turns 50! A Celebration of a Special Park
05/27/2019
more...
Family hike
05/27/2019
more...
Al Anon meeting
05/29/2019
more...
Sonoma Speaker Series features Tony award-winner McKechnie
05/29/2019
more...
Oakmont Farmers Market
06/01/2019
more...
Sierra Garden now open near Oakmont
06/01/2019
more...
Come to the Bennett Valley picnic!
06/02/2019
more...


Weather Underground PWS KCAKENWO2